[ Securities America Headquarters ]
Location:
Port Grace Blvd & Southport Parkway
LaVista, NE
General Contractor:
Kiewit Building Group
Precast Supplier:
Enterprise Precast Concrete, Inc.
Contact:
John Arehart, General Manager
Enterprise Precast
The project consisted of 79 precast wall panels with brick face. The average panel weight was 28,000 lbs. Panels were 32’ high and erected mostly in windy conditions. The project was completed two days ahead of schedule. Both the General Contractor and Precast Supplier were extremely pleased.